Reason for submission: Protesting of PG&E’s motion and failure to comply with our requested ruling to restore access to the PV RAM interconnection maps

View or download comments

This filing represents the Clean Coalition’s protest of Pacific Gas & Electric’s (PG&E) motion and failure to comply with our requested ruling to restore access to the PV Renewable Auction Mechanism (RAM) interconnection maps pending release of the delayed new interconnection capacity assessment (ICA) maps. PG&E filed a motion requesting a three week extension to comply, and then complied the next day.